Thursday, December 20, 2018

Linden Grove New Berlin Update

 Construction continues on the Linden Grove New Berlin CBRF addition.  Siding on the exterior is wrapping up. On the interior, drywall and painting finishes up, while the restroom tile floors go in.




Monday, December 3, 2018

Mukwonago Animal Hospital

See the progress we've made on the Mukwonago Animal Hospital Addition.  The concrete slab is poured, steel columns and beams installed, and rough framing continues on this 4,600 square foot addition.